New and Used Car Talk Reviews Hot Cars Comparison Automotive Community

The Largest Car Forum in the Philippines

Page 1 of 6 12345 ... LastLast
Results 1 to 10 of 59
  1. Join Date
    Aug 2006
    Posts
    381
    #1
    Hello mga fellow tsikoters,

    May quick question lang ako, kasi regarding buhos ng 2nd floor slab..

    Manual kasi gagawin ng mga tauhan namin, mga nasa 70sqm ang area bubuhusan nila ng semento, now my question here..

    Kailangan ba nila buhusan lahat in a day? Or pwede half the area muna then bukas ulit yung other half?

    Any inputs would be greatly appreciated..

    Kasi ang sabi sakin ng foreman ko ay pwede raw half muna then bukas yung other half, my point here is that pano nila e half yun?

  2. Join Date
    Jul 2011
    Posts
    1,711
    #2
    Sa malilit na floor slab pwede po basta ung floor slab mo ay suported ng beam, normally ung sa ibabaw ng beam ang putol.

    Sample, ang bubuhusan mo ay 2.5m x 7.5m, ang beams mo ay every 2.5m, pwede po na ang buhusan mo muna ay 2.5m x 2.5m.


    Pero pag malaking area, ung magkakalayo ang beams mo, mahirap po pag naputol ang buhos bago umabot sa beam, consult po ninyo sa civil engineer na gumawa po ng design ng haws nyo kung saan safe. Pero it is cheaper to hire additional manpower para isang buhusan lang.

  3. Join Date
    Sep 2005
    Posts
    3,829
    #3
    Pwede yan basta ang putol eh sa beam.

  4. Join Date
    Aug 2006
    Posts
    381
    #4
    That you sa reply, ang ibig niyo niyo po sabihin ay sa gitna ng beam ang half buhos? Or before mag beam?


    Also hinde poba ma sacrifice ung tibay nun pag half half yung buhos?

  5. Join Date
    Aug 2009
    Posts
    178
    #5
    Quote Originally Posted by earthlyken View Post
    Hello mga fellow tsikoters,

    May quick question lang ako, kasi regarding buhos ng 2nd floor slab..

    Manual kasi gagawin ng mga tauhan namin, mga nasa 70sqm ang area bubuhusan nila ng semento, now my question here..

    Kailangan ba nila buhusan lahat in a day? Or pwede half the area muna then bukas ulit yung other half?

    Any inputs would be greatly appreciated..

    Kasi ang sabi sakin ng foreman ko ay pwede raw half muna then bukas yung other half, my point here is that pano nila e half yun?
    If 4inches lang ang thickness ng floor slab mo sir, kayang kaya yan buhusan ng minsanan coz that is more or less be equal to about 7 cu. m. of concrete plus of course volume of concrete required for the beams and columns. By doing this, you can avoid "cold joints" or "construction joint/s" and have your floor slab "monolithic". Better add some extra manpower and hire a one bagger mixer to do this. hope to help.....

  6. Join Date
    Sep 2005
    Posts
    3,829
    #6
    Ok lang yan basta gitna ng beam ang putol, walang sacrifice sa tibay yan.

    Although since 70sqm lang naman yung bubuhusan nyo eh mas maganda kung buo na.

  7. Join Date
    Oct 2002
    Posts
    10,820
    #7
    kaya yan 1 day, dagdag ka ng tao saka mixer. parehas din naman gastos mo sa manpower, kasi imbes na 2 days bayaran mo maging 1 day na lang doble lang tao.

  8. Join Date
    Oct 2002
    Posts
    17,340
    #8
    ^Dapat i-charge niyo na ng consultation fees si TS para sa house construction nila. :D

    I agree that this can be done in one day basta maayos yung pag-prepare ng forms na bubuhusan.

  9. Join Date
    Jul 2011
    Posts
    1,711
    #9
    mas makakatipid ka kung isang buhusan lang, isipin mo per hour ang bayad sa tao, plus kung sa 2nd day ung mga construction boys mo ay magsabi na masakit ang katawan nila at hindi makapagtrabaho, paano na ang floor slab mo? helper lang naman ang idadagdag mo, ung taga halo at taga deliver ng concrete.

    Saka after buhos normally day-off ang mga tao para rest while curing ung concrete, except meron sila magagawang iba sa haws mo na kakain ng 1 day.

  10. Join Date
    Aug 2006
    Posts
    381
    #10
    Ok na yung poste then their planning to buhos the beam but d sagad para may maisingit ung mga bar para mabuhusan yung flooring ng 2nd floor, kaso ang sabi nila ay to save mga coco lumber raw ay half now and half the nextday ung buhos ng flooring.. ok lang bayun na ganun procedure? Am just curious kung pano nila buhosan half ng biga? Lalagyan ng harang yung other half ng biga?

Page 1 of 6 12345 ... LastLast

Tags for this Thread

Slab concrete pouring