    Not about a new post nor a new transformer, but a far similar encounter with Meralco here.

    Almost a decade ago, when we had our new house built, the Meralco post was a meter inside our property frontage. It will not look good and will not work with our house/garage plan and so I had it moved on the property boundary. It is a good thing that I did not request to move it an inch further, as I bought the adjacent parcel of lot last year.... It cost me around P25K(?) then.




    23.2K:veiledsmile1:

  2. Join Date
    Apr 2013
    Posts
    360
    #12
    isa sa client namin dati nangyari ito. quiapo area siya nagpatayo ng bahay, parehas sabi ng meralco na kailangan niya i-shoulder yung bagong transformer. di daw kaya ng capacity ng existing transformer yung load ng bahay nya (may mini-theater, all rooms w/ AC, pump para sa pool, etc)...

    so ang ginawa namin is to minimize the load computation sa drawings (for meralco only), bale kunyari regular house load lang. so approved na, then after a month nung nakalipat na sila ang balita e lagi daw nagpa-fluctuate yung kuryente sa area. edi nagdagdag ng transformer yung meralco na hindi sagot ng may-ari ng bahay.