March 17th, 2021 09:04 AM #11
Creditors daw are calling na kaya ang sounded the alarm. Baka iyong ibang projects ng smc, pati iyong airport sa bulacan, kinakatakutan ma-apektuhan siguro kaya nag exert na ng pressure via the closure announcement kahapon.
"He said the TRB insisted that 100 percent of Skyway 3’s ramps should be finished even if the SMC contract allowed it to collect toll only when 95 percent of the entire project has been finished.
“The quickest way for our infrastructure unit to speed up 100 percent completion of the ramps would have been to close Skyway 3,” Ang said."
"SMC said on Tuesday that 10 of the 26 ramps were open and these comprised a “small portion” of the project and did not affect the 97 percent completion rate."
SMC, TRB clash over Skyway 3 toll collection | Inquirer Business
do what you gotta do so you can do what you wanna do