Results 1 to 10 of 52
-
February 2nd, 2013 01:17 AM #1
what I heard from the news.
- It will be 3 phases, phase 1 is from pasay to megamall, phase 2 is from megamall to north ave. phase 3 is from north ave. to balintawak
- will take 12 months to 23 months, 12 months kung round the clock ang paggawa, will start may 2013
- will use high grade asphalt, according to them can last 10 years without maintenance, unlike sa ginagamit nila sa coastal road na konting uilan eh lubak na naman
- will build a flyover both for nb and sb of edsa taft, which they identified as the heaviest bottleneck of edsa, thank god, i passby this bottleneck everyday, 11pm na ng gabi traffic pa rin dyan.
- will also build elevated bus loading and unloading platform, i hope this solves the problem where bus takes 3 lanes and 1 lane left for 3 lane trafic to merge.
- at least 3 lanes will be left open at any point of edsa, around 150 meters per work station.
- 50+ alternate routes have been identified.
my reaction, im excited and at the same time dreading this project, excited kasi after this mababawasan travel time ko (hopefully, else it will be a waste of P3.4 billion), dreading kasi i pass by edsa everyday, im planning to take alternate route but the traffic may also spread around edsa, like c5 and manila route. at yung edsa taft flyover construction ngayon pa lang grabe na traffic dyan lalo na during construction, pero sabi nga nila pag may tyaga, may nilaga.
here's hoping this only takes 1 year.
-
February 2nd, 2013 01:49 AM #2
-
February 2nd, 2013 06:10 AM #3
I wonder how much worse the traffic will get when construction begins. I'm so thankful I don't need to pass EDSA anymore.
-
February 2nd, 2013 07:12 AM #4
I agree na biggest bottleneck ang Edsa Taft area. Good thing na gagawan nila ng flyover para dito.
Downside is yun nga, yun heavy traffic na i-gegenerate nito once na mag-start at sakto pa ito sa umpisa ng classes.
Gusto ko rin makita yun gagawin nilang solution sa heavy traffic ng Cubao area.
-
February 2nd, 2013 09:35 AM #5
Sigurado sobrang traffic nito. Mga galing south area (slex, alabang, sucat, bicutan) brace yourself. baka hinda pa umabot sa nichols toll plaza traffic na pag nag umpisa na.
Dapat kasi from the start puro elevated na ang MRT pati terminal. tingnan mo tuloy nangyari sa EDSA rotonda pasay galing MOA. Gibain buong MRT tapus gawing elevated na lahat tapus ayusin Magallanes interchange pati Guadalupe area, Crossing area, Ortigas area, Cubao area, etc
-
February 2nd, 2013 09:45 AM #6
Siguradong isang taon na tiis to sa traffic, but we have to support the government in this wonderful initiative.
-
February 2nd, 2013 09:50 AM #7
Dapat buksan mga posh subdivisions para magamit yung roads as alternative routes...
-
February 2nd, 2013 10:03 AM #8
-
February 2nd, 2013 10:39 AM #9
-
February 2nd, 2013 01:54 PM #10
frm Tof Gaer Phils
so ganyan din ba ang asphalt na gagamitin? glossy, hehe :D
The serpentine belt is still okay, usual consumables (air filter, oifl filter, cabin filter) got...
Ford Everest 2015