Results 1 to 6 of 6
-
August 18th, 2012 02:16 PM #1
BRIEF BACKGROUND
Extension of the existing 20.7 km. LRT Line 1 by approximately 11.7 km. from Baclaran to Bacoor including the initial Rolling Stock (55 train sets).
Eight (8) passengers stations with a provision for two (2) additional stations; one (1) satellite depot and three (3) Intermodal facilities.
Operations and Maintenance Concession of the integrated line with systems enhancement works throughout the concession period.
ESTIMATED PROJECT COST : P 61.53 Billion
GOP P 30,593.63 Million
Private Sector
P 30,934.18 Million
Implementation Scheme: Public Private partnership (PPP) Financing Arrangement
GOP/Public sector components shall be through Official Development Assistance (ODA) from JICA and National Government Subsidy Appropriation.
STATUS OF THE PROJECT (as of June 8, 2012)
Posting of Invitation to Pre-qualify and to Bid - June 4, 2012 on the following components
Operation and maintenance of the Existing System;
Design, Procurement, engineering, Construction, Installation, Completion, Testing and Commissioning of the Cavite Extension facilities (Cavite Extension System);
Integration of the Existing System and the Cavite Extension System (Integrated System);
Operation and Maintenance of the Integrated System; and
System Enhancement Works covering whole-of-life investments for the Integrated System.
The Environmental Management Bureau (EMB) is requiring LRTA to submit the Environmental Impact Statement (EIS) aside from Environmental Performance Report Management Plan (EPRMP) which was submitted to them on April 26, 2012
Acquired 80.33% or 206,886 sqm. of private and public lots for the Right of Way (ROW). Negotiation with the private property owners is on-going.
Site Acquisition, Site Grading, Construction of Fence and Slope Protection, Roads and Water System, Drainage System and construction of 180 housing units for resettlement site of informal settlers were completed.
Negotiation for the construction and completion of the remaining 1,820 housing units is on-going with the local government units of Cavite.
TARGET IMPLEMENTATION SCHEDULE:
ACTIVITY
DATE
NEDA Approval March 2012
Bidding Process March - November 2012
Expected Date of Award/ Effectivity December 2012
Start of Construction (Phase 1) April 2013
Start of Construction (Phase 2) April 2015
Commissioning Phase 1(Baclaran to Dr. Santos Ave. Station) May 2015
Commissioning Phase 2(Dr. Santos Ave. Station to Niyog Station) May 2017
-
August 18th, 2012 02:20 PM #2
The 25 firms that bought the pre-qualification documents were:
1.San Miguel Infra
2.Macquarie Group
3.Mitsubishi Corp.
4.D.M. Consultant, Inc.
5.Hanjin Heavy Industries & Construction Co. Ltd.
6.Sumitomo Corp.
7.Leighton Contractors
8.Sycip Salazar Hernandez & Gatmaitan
9.FSG Capital Inc.
10.EFC Enterprises
11.FF Cruz & Co. Inc.
12.Marubeni Corp.
13.BPI Capital Corp.
14.ING Bank
15.Jorgman Planning & Development Corp.
16.RATP Development
17.Benchtel Overseas Corp.
18.Comm Builders & Technical Philippines Corp.
19.Lenvoisa Construction Inc.
20.APT Global Inc.
21.Makati Development Corp.
22.Tranzen Group
23.SERCO Group
24.Cathay Energy Service Corp.
25.SYSTRA Group
DOTC extends bid deadline for P60-B LRT project
http://www.abs-cbnnews.com/business/...-b-lrt-project
-
October 23rd, 2012 09:41 AM #3
Only 4 groups may qualify for LRT 1 extension project bidding
MANILA - (UPDATE 2, 5:30 p.m.) Only four out of the six companies that submitted pre-qualification documents for the bidding of the Light Rail Transit Line 1 Cavite Extension Project can move on to the next step, the Department of Transportation and Communications said on Monday.
The 4 firms include DMCI Holdings Inc., Light Rail Manila Consortium, MTD-Samsung Consortium and San Miguel Infrastructure Resources Inc.
DMCI's partners are Marubeni Corp. and Sistema Tranporte Collectivo Metrorey.
Light Rail Manila is composed of Metro Pacific Investments Corp, which has a 33 percent stake; Ayala Corp, 33 percent; AC Infra Holdings Corp, 12 percent; Macquarie Infra Holdings Philippines PTE Ltd, 10 percent; and RATP Development SA, one participation unit. The group’s railway infrastructure would be handled by Bouygues travaux Publics SA, Obrascon Huarte Lain SA, and Leighton Contractors Asia Ltd, while the railway system would be handled by Alstom Transport SA and Ansaldo STS PA. The operation and maintenance would be handled by RATP Development SA.
San Miguel Infra Resources Inc. is composed of GS Engineering and Construction Corp and POSCO Engineering and Construction Co Ltd. The railway set will be taken care of POSCO Engineering and the railway system by Korea Railroad Corp.
The MTD-Samsung Consortium is composed of MTD Capital Bhd, which owns 33 percent; Samsung C&T Corp, 20 percent; Union Equities Inc, 15 percent; DM Wenceslao & Associates, 12 percent; and Primewater Infra Corp, 20 percent. The railway infrastructure will be handled by MTD Capital and Samsung C&T, while the system will be provided by Hyundai Rotern Co. The operation and management will be handled by Seoul Metro.
Ecorail and Luzon Rail Transit System failed to make it to the 2 p.m. deadline for the submission of the pre-qualification documents, said DOTC Undersecretary Jose Perpetuo M. Lotilla, who heads the Special Bids and Awards Committee.
"The rule is very clear, and it is all or nothing proposition. The decision is not to acept the two bids' pre-qualification documents for having been submited beyond the deadline," he said.
Earlier, the DOTC extended twice the deadline for submission of pre-qualification documents. From August 22, the deadline was moved to September 28, then to October 22.
Costing P30 billion, the southbound extension of LRT 1 will increase the train's span from 20.7 kilometers to 32.4 kilometers, with approximately 10.5 kilometers of the extension elevated and 1.2 kilometers at grade. The remaining P30 billion will be used to acquire up to 39 new light rail vehicles to avoid the need for raising fares.
DOTC said more than 500,000 commuters use LRT 1 everyday. The existing line runs from Baclaran in Pasay City to Roosevelt in Quezon City. The southern part of Metro Manila and neighboring Cavite province is home to nearly four million people.
The DOTC tapped International Finance Corp. and state-owned Development Bank of the Philippines as transaction advisors. The project has five components:
- Operation and maintenance of the existing system, which includes operation and maintenance of depot, electrical and mechanical system, rolling stock, station, track, and other related assets;
- Design, procurement, engineering, construction, installation, completion, testing, and commissioning of the Cavite extension facilities;
- Integration of the existing system and the Cavite Extension System, including train control and signaling, communications, and traction power supply;
- Operation and maintenance of the integrated system; and
- System enhancement works covering whole-of-life investments.
The project is the government's fourth public-private partnership venture to be bid out since the program was announced in November 2010. Last year, the government awarded the P1.956 billion Daang Hari-Slex Link Road Project to Ayala Corp.
The P16.42 billion PPP for School Infrastructure Project of the Department of Education was awarded to the consortium of Citicore Holdings Investment Inc.-Megawide Construction Corp, Inc. and to the joint venture of BF Corp.-Riverbanks Development Corp.
The P15.86 billion NAIA Expressway is still in the pre-qualification stage.
Light Rail Manila is a joint venture between Ayala Corp and Metro Pacific Investments Corp. Manuel V. Pangilinan chairs both MPIC and TV5, of which InterAksyon.com is the online news portal.
-
Verified Tsikot Member
- Join Date
- May 2011
- Posts
- 191
-
October 23rd, 2012 09:53 AM #5
-
3M Color Stable series are all above 50% TSER. RFID readable through the tint, stays good for...
What's the best car tint brand and color?